• Invitation to Bid

PROVISION OF FENCE AT RIGHT SIDE OF ENTRANCE GATE, REPAIR OF PLANT BOXES WITH IRON GRILL AND REPAINTING OF EXISTING FENCE AND CATWALK @ 5TH STREET, PORT OF CEBU.


Date : June 19, 2007

INVITATION TO PAKYAW GROUPS

The Cebu Port Authority (CPA) through the Engineering Services Department is inviting Pakyaw Groups (Labor and Equipment) to apply for the various items of works involved in the proposed PROVISION OF FENCE AT RIGHT SIDE OF ENTRANCE GATE, REPAIR OF PLANT BOXES WITH IRON GRILL AND REPAINTING OF EXISTING FENCE AND CATWALK @ 5TH STREET, PORT OF CEBU under the following contracts:

Item
Qty. Unit

Description

Unit Cost
Total Cost
I
L.S.
Demolition of Concrete/ Excavation for Footing,Zocalo and Disposal
76,965.00
76,965.00
II
L.S.
Installation of Forms and Rebars and Pouring of Concrete for Foundations, Columns and Zocalo
146,632.50
146,632.50
III
L.S.
CHB Laying, Plastering and Provision of Concrete Lintel Beam
55,650.00
55,650.00
IV
L.S.
Painting of New Fence, Plant Boxes, Repainting of Existing Fence and Covered Catwalk
58,800.00
58,800.00
V
L.S.
Repair of Plant Boxes, Fabricate and Install of Iron Railings along Newly Repaired Plant Boxes
68,754.00
68,754.00

PROJECT DURATION : 67 Calendar Days

Equipment Requirements: Dump Truck (6W), Hauling Truck, Cut-off Wheel Machine, Jackhammer with Aircompressor, Bar Cutter, Welding Machine, One-bagger Concrete Mixer

Application forms are available at the Office of the Engineering Services Department, Cebu Port Authority. The Deadline for the submission of application forms will be on June 21, 2007. Qualified PAKYAW GROUPS will be noted for their employment on/before June 25, 2007. The implementing Agency, through the Engineering Services Department, reserves the right not to accept and/or process application forms received after the above deadline.

MARIO G. TAN
BAC Chairman

Noted by :

ANGELO C. VERDAN
General Manager

 